Use case: procurement
One real process, step by step: who does each step, what they see, and what is recorded.
Scroll, or press the button on each card. These are real Wosool cards, with example data, and each one waits for its owner.
Demonstrated: built and tested. Example data
Spare-part request
Technical report (optional)
Quotations: ball bearing 6205
Due: 07/11/2026
Quotation: trial supplier A
Quotation: trial supplier B
Specification sheet
Approve the purchase request: ball bearing 6205
Due: 05/11/2026
Receiving: ball bearing 6205
Due: 10/11/2026
Delivery note
Someone in maintenance asks for 4 ball bearings and a mechanical seal: the parts, the quantities, and a technical report if there is one. The request gets its own reference, and anyone can see where it is.
Press the card's button to move to the next step.
Procurement collects the quotations, each attached to the supplier who sent it, with the datasheet, and chooses the supplier. The green edge means there is time: it is due in 3 days. Anything missing is listed on the card.
Cost control sees exactly what it is deciding: the parts, the supplier, the value and the request number. It approves, or returns the request for budget, at most twice before the project manager decides. Nothing moves until it decides.
After the order, the supplier's confirmation and the payment, the warehouse receives the parts on the supplier's delivery date, with the delivery note. The request closes, and the record keeps who did each step, and when.
Closed. Four steps, each with its owner, and every signature on record.
Simplified to four stages from the 12-step spare-part cycle.
Purchasing in Wosool ran on a real company between 8 and 10 September 2026, from the request to the price received:
Proven in production, 8 to 10 September 2026
Demonstrated: built and tested
Example: one request, with example data
| When | Who | What |
|---|---|---|
| Sun 09:10 | Requesting department | Asked for 2 bearings and 1 seal |
| Mon 11:40 | Procurement | Added two quotations and chose a supplier |
| Mon 13:05 | Requesting department | Raised the purchase request |
| Mon 15:20 | Cost control | Approved |
| Tue 10:00 | Procurement | Issued the purchase order |